Cross-section enlargement of an existing 515-meter-long tunnel (expanding from a 5×5-meter cross-section to 12×8 meters).
Installation of self-drilling micropiles and steel ribs at the portals. Excavation is carried out entirely using drilling and blasting, primary support with fiber-reinforced shotcrete, installation of 6-meter-long resin-grouted friction bolts, and a final layer of unreinforced shotcrete. The lining includes waterproofing and installation of reinforcing steel along the entire length of the tunnel, followed by concrete placement using a 9-meter-long traveling formwork.