VL5 UPGRADING PHASE 2_4

VL5 UPGRADING PHASE 2

Client:

Alto Maipo

The main activities to be carried out in the tunnel consist of installing three types of ground support (Type L1, Type L2, and Type L3) depending on the damage present, with the following characteristics:

Type L1 Support (length 20 m): corresponds to a transition zone where shotcrete + welded wire mesh and spot bolts will be installed.

Type L2 Support (length 30 m): corresponds to a zone where shotcrete + bolts + welded wire mesh + horseshoe-type

lattice girder + welded wire mesh + shotcrete will be installed.

Type L3 Support (length 20 m): corresponds to a zone where shotcrete + bolts + welded wire mesh + circular

lattice girder + welded wire mesh + shotcrete will be installed.

Final lining for Las Lajas Headrace Tunnel (2,000 m)

Technical specifications

Date:

Start:

01 - 2025

End:

10 - 2025

Country:

Chile

Province:

Maipo

Municipality:

San Jose de Maipo

Excavation type:

-

Geometry:

Cross-section:

Túnel Hidráulico

Length:

-

Overburden:

-

Budget:

15.878.454 €

Construction method:

Traditional support (Shotcrete+Bolts+Mesh+Girders+Mesh+Shotcrete) for Type L2 and L3 Collapses, Las Lajas Headrace Tunnel

Geology and geotechnics:

-

Machinery used:

  • 1 Jumbo M2C
  • 1 Radial Jumbo (Simba)
  • 2 Telehandlers
  • 1 Front Loader
  • 1 Excavator
  • 2 Water Trucks
  • 3 Dump Trucks (Tipper)
  • 2 Mixer Trucks
  • 1 Roboshot
  • 1 Concrete Pump