Excavation and ground support of 13,786 meters of drifts and 487 meters of shafts over a 5-year period. Three drift cross-sections are defined: main ramp (6.0×5.5), waste rock drifts (5.5×5.5), and ore access drifts (5.0×5.0). Two of the shafts will be excavated from the surface using a 3.6mØ raise boring method, totaling a length of 148 m. The remaining shafts will feature a 3.0×3.0-meter section and will be developed between underground levels using suspended blast charges. Ground support for drifts and shafts will consist of shotcrete, rock bolts, wire mesh, and steel sets.