Pouring of 177,782.72 m³ of concrete across sections within stations and tunnels on Lines 2 and 4 of the Lima Metro, including the installation of drainage pipes, electrical conduits, manholes, and ballast mats. Additionally, segments and two-component grout are removed at each station following the passage of the TBM.