Line 7 of the Santiago Metro runs between the communes of Renca and Las Condes, in the Santiago Metropolitan Region. The construction of this line consists of 6 sections; within section 1, Metro decided to create two subsections: 1B and 1C.

Section 1B is approximately 2,650 m long and includes two stations (Huelén and Neptuno) and two ventilation shafts (PVF-04 and PVF-05).

Work is scheduled across 5 headings—1 single and 2 double. Muck removal must be carried out through the access shafts, requiring sufficiently powerful hoisting equipment to ensure debris clearance proceeds on schedule.

Due to ground conditions, excavation will be executed by mechanical means, with ground support comprising steel mesh, shotcrete, and steel sets, using 1-meter advance lengths.

Technical specifications

Date:

Start:

02 - 2026

End:

11 - 2027

Country:

Chile

Province:

Santiago Metropolitan Region

Municipality:

Cerro Navia

Excavation type:

Soils

Geometry:

Cross-section:

66 m²

Length:

2.650 m

Overburden:

-

Budget:

1.294.461,90 UF

Construction method:

NATM

Geology and geotechnics:

Pumicites

Machinery used:

  • PM500 shotcrete robots
  • 13 t and 20 t backhoe excavators
  • Cat 320 excavator with hammer
  • CAT 950 type wheel loaders
  • 20 t tower cranes
  • Rotating and fixed telehandlers