RESTORATION OF RAMA COLORADO TUNNEL AND ADIT 7

Client:

AES Chile

Access tunnel (adit 8) measuring 4.20 x 4.50 m in certain sections, restricted by a 2.5 m diameter water pressure plug. The repair consists of removing shotcrete from both the sidewalls and the crown, floor chipping, and the reinstatement of shotcrete + mesh + bolt and plate. Double mesh will be placed in the floor concrete. The project includes surface site facilities comprising offices, a meeting room, a changing room, mechanical and electrical workshops, showers, a dining hall, and parking and material storage areas, as well as electrical, water, communications, air, and fuel services.

Technical specifications

Date:

Start:

02 - 2025

End:

09 - 2025

Country:

Chile

Province:

Metropolitan Region

Municipality:

San José

Excavation type:

Tunnel repair with Bolt + Mesh + Shotcrete and Steel Sets support

Geometry:

Cross-section:

Túnel Colorado 3,5 x 3m; Túnel Ventana 7: 3,45 x 2,7

Length:

-

Overburden:

1,570 m

Budget:

USD 6.435.314

Construction method:

Mechanized demolition (scaling type) in collapsed sections and installation of ground support.

Geology and geotechnics:

A rock mass with highly isotropic structures featuring Type II, III, and IV rock, in addition to the humidity generated by the tunnel conditions.

Machinery used:

  • Lifting equipment, 1 m3 dumper
  • Manual drills
  • Multifunctional equipment (Brokk)
  • Compressor
  • Generators
  • Light equipment
  • Tk-40 concrete pump
  • Mini-excavator
  • LHD-203