MINERA PANAMÁ TUNNEL

Client:

FIRST QUANTUM MINERALS

FIRST QUANTUM MINERALS

1,200 m tunnel for tailings management in mining operations. Section 4.5 x 5.7 m. Includes slab and 1.2 m high walls reinforced with 20 cm thick mesh. Includes 279 m adit.

Technical specifications

Date:

Start:

09 - 2023

End:

05 - 2025

Country:

Panama

Province:

Colón

Municipality:

-

Excavation type:

Tunnels

Geometry:

Cross-section:

4,5 x 5,7 m

Length:

1.200 m.

Overburden:

80 meters

Budget:

10.365.968 USD

Construction method:

Drill and blast

Geology and geotechnics:

Granodiorite

Machinery used:

  • Epiroc 282 Jumbo
  • Epiroc ST1030 Loader
  • MT2200 Truck
  • Putzmeister SPM4210 Robot