Line 7 of the Santiago Metro runs between the communes of Renca and Las Condes, in the Santiago Metropolitan Region. The construction of this line consists of 6 sections; within section 1, Metro decided to create two subsections: 1B and 1C.
Section 1B is approximately 2,650 m long and includes two stations (Huelén and Neptuno) and two ventilation shafts (PVF-04 and PVF-05).
Work is scheduled across 5 headings—1 single and 2 double. Muck removal must be carried out through the access shafts, requiring sufficiently powerful hoisting equipment to ensure debris clearance proceeds on schedule.
Due to ground conditions, excavation will be executed by mechanical means, with ground support comprising steel mesh, shotcrete, and steel sets, using 1-meter advance lengths.