In this video, you can see the progress of the El Duranguense road tunnel, which OSSA is currently executing in Durango (Mexico). The project involves widening the section of an existing 515-meter-long tunnel (increasing from a 5×5 meter section to a 12×8 meter section). Excavation is carried out entirely using drill and blast, with primary support consisting of fiber-reinforced shotcrete, the installation of 6-meter-long friction bolts injected with resin, and a final layer of shotcrete without fibers. For the lining, waterproofing and reinforcement steel are placed along the entire length of the tunnel for subsequent concreting using a 9-meter-long formwork traveler.