NEOM SPINE INFRASTRUCTURE – RUNNING TUNNELS (MOUNTAIN SECTION) LOTS 2 AND 3

Client:

FCC Construcción S.A.

The NEOM project consists of the construction of a new city in northwestern Saudi Arabia, on the Red Sea coast. This requires the construction of two parallel railway tunnels, one for passengers and another for freight.

OSSA will execute 2 tunnels of 3,200m each (160m² section), the 2,340m Adit 3N (80m² section), and the 140m Adit junction (380m² section).

Technical specifications

Date:

Start:

04 - 2023

End:

07 - 2025

Country:

Saudi Arabia

Province:

Tabuk

Municipality:

Tabuk

Excavation type:

Adit, 2 tunnels, and 1 cavern

Geometry:

Cross-section:

160 m²

Length:

2 x 3.200 m

Overburden:

600 m

Budget:

38.511.922 €

Construction method:

Drill and blast (NATM)

Geology and geotechnics:

Granites

Machinery used:

  • PUTZMEISTER SPM-500 shotcrete robot
  • EPIROC XL3C drilling jumbo
  • EPIROC E2C drilling jumbo
  • CATERPILLAR CAT-980 wheel loaders